10 years and doubled cost: The four-laning saga of Mangaluru-Bengaluru NH 75 in Dakshina Kannada and Hassan

Source Entity

India Latest News: Top National Headlines Today & Breaking News | The Hindu

November 26, 2026
10 years and doubled cost: The four-laning saga of Mangaluru-Bengaluru NH 75 in Dakshina Kannada and Hassan

The Mangaluru-Bengaluru NH 75 expansion project has seen costs nearly double to ₹2,220 crore over a decade. Despite significant delays and construction hurdles, the four-laning has successfully reduced travel time between Hassan and Mangaluru.

The Decade-Long Transformation of NH 75

The expansion of National Highway 75 (NH 75), the vital artery connecting Karnataka’s capital, Bengaluru, to the coastal hub of Mangaluru, stands as a testament to the complexities of large-scale infrastructure development in India. Spanning over 115 km between Hassan and B.C. Road in Dakshina Kannada, the project has been characterized by both significant engineering progress and profound logistical challenges. As the state nears the completion of this four-laning initiative, it is essential to examine the fiscal and operational trajectory of this corridor.

Fiscal Escalation and Project Economics

The financial profile of the NH 75 widening project has undergone a dramatic transformation. Originally estimated at approximately ₹1,220 crore in 2017, the project’s final cost has ballooned to nearly ₹2,220 crore by the end of 2026. This near-doubling of expenditure highlights the inflationary pressures, material cost surges, and administrative delays that frequently plague long-term road projects. Such fiscal variance often necessitates complex renegotiations with contractors and additional budgetary allocations, reflecting the volatility inherent in massive civil engineering endeavors.

The Human Cost of Infrastructure Delays

Beyond the balance sheets, the human element of this decade-long saga cannot be ignored. Between 2018 and 2021, the project faced near-total stagnation, turning the commute between Mangaluru and Hassan into a harrowing experience for residents and freight operators alike. This period of inactivity not only hindered regional economic connectivity but also imposed a significant 'ordeal' on road users who navigated incomplete, hazardous stretches. The transition from a 'nightmarish' commute to a streamlined corridor is a relief, but it serves as a stark reminder of the social cost of construction delays.

Operational Improvements and Connectivity

The tangible benefits of this endeavor are finally becoming apparent. With the majority of the 115 km stretch successfully converted into a four-lane highway, the travel time for passenger vehicles has dropped from five hours to approximately three to four hours. This reduction is a major win for regional logistics, facilitating smoother movement of goods between the hinterland and the New Mangalore Port. Enhanced connectivity is expected to boost local commerce and tourism, provided the corridor remains well-maintained.

The Shiradi Ghat Bottleneck

Despite the progress, the project remains incomplete due to the 26-km Shiradi Ghat stretch between Maranahalli and Addahole. This specific segment represents the most challenging engineering frontier of the entire highway. As a critical mountain pass, the Shiradi Ghat requires specialized geological considerations that differentiate it from the flatter, more predictable terrains of the rest of the highway. The exclusion of this stretch from the current four-laning success story underscores the ongoing difficulty of balancing infrastructure expansion with the sensitive ecological and topographical demands of the Western Ghats.

Future Outlook and Strategic Implications

Looking ahead, the completion of the NH 75 expansion serves as a blueprint for future infrastructure projects in Karnataka. The lessons learned from the cost overruns and the multi-year stagnation are invaluable for policymakers aiming to streamline the tendering and execution phases of road transport initiatives. While the highway now offers a significantly improved transit experience, the final resolution of the Shiradi Ghat segment remains the next critical milestone to ensure the full potential of the Bengaluru-Mangaluru corridor is realized.